India’s Leading Domain & Web Hosting Provider
Ceramics maker moves 64 out-of-support Hyper-V guests to Azure on Windows Server 2022
Tile and sanitaryware maker, 3 kiln sites, dealer network of 1,100 · Morbi, Gujarat, India · 12 weeks
As-is situation
The company ran 64 VMs on a three-node Hyper-V failover cluster built on Windows Server 2012 R2, managed by an old SCVMM instance. Thirty-eight guests also ran 2012 R2, including the dealer ordering portal, a design catalogue server holding 2.3 TB of tile renders, and the kiln energy reporting database. With ESUs ending on 13 October 2026, the auditors flagged the estate. The shared SAN was single-controller and had failed once during peak dispatch season, stopping dealer orders for five hours.
- 38 guests and all hosts on Windows Server 2012 R2 with no ESU coverage after October 2026.
- A single-controller SAN caused a 5-hour dealer ordering outage in peak season.
- Kiln energy reports fed state electricity rebate claims and could not lose history.
Approach, tools and architecture
NTSPL upgraded each 2012 R2 guest to Windows Server 2022 on a cloned VM, tested the application, then replicated the upgraded VM with Azure Migrate's Hyper-V provider into Azure Central India. Generation 1 VMs were kept as Gen 1 where UEFI conversion broke legacy apps. Existing Windows Server Datacenter licences with Software Assurance were applied through Azure Hybrid Benefit. The kiln reporting database got Azure Backup with long-term retention, and Azure Arc now covers the two plant-floor servers left on site.
Implementation approach
Measured results
Operational improvements
- Monthly patch compliance is reported from Azure Update Manager instead of manual host checks.
- Dealers open tile renders faster from the catalogue site.
Cost considerations
Using Hybrid Benefit kept Windows licence cost flat. The main one-off cost was OS upgrade testing, about 40% of total effort. Plant-floor servers stayed on site with Arc management at a small per-server monthly charge.
Return on investment
Avoiding a new SAN and three replacement hosts saved about INR 52 lakh in capex. Azure run cost is similar to the old AMC and power bill, so the payback came from avoided hardware within the first year.