AWSTwo-wheeler OEM component supplierManufacturing & Industrial

Two-wheeler parts supplier converts 142 vSphere VMs to EC2 instead of a 3.4x renewal

Tier-1 supplier of braking and suspension parts, 5 plants, 3,800 employees · Pune and Hosur, India · 16 weeks

Amazon Web Services
01

As-is situation

The supplier ran 142 VMs on two vSphere 7 clusters at its Pune head office: SAP Business One, a Java-based PPAP and quality portal, an OEM EDI gateway, file servers, and test environments. Its VMware renewal under the new VCF bundle came in at 3.4 times the previous support cost. The vSAN nodes were also four years old. Nineteen VMs carried snapshot chains older than a year, and eleven still used BIOS boot with LSI Logic controllers that the target instances would not boot.

  • VMware renewal at 3.4x previous cost, due in 18 weeks.
  • 19 VMs with snapshot chains over a year old, two of them on the EDI gateway.
  • OEM EDI delivery schedules allowed no more than 2 hours of gateway downtime.
02

Approach, tools and architecture

NTSPL ran a pre-flight on all 142 VMs, consolidated snapshots and installed Nitro-compatible drivers before replication. AWS Transform for VMware generated the first wave plan and VPC layout from vCenter data, which the team adjusted for plant shift timings. Application Migration Service converted 128 VMs to EC2 in Mumbai; 14 test VMs were retired. The EDI gateway moved in a 70-minute Sunday window after a full test cutover the week before. SQL Server licences were tracked in License Manager to prevent over-deployment.

RVTools export → guest pre-flight → AWS Transform wave plan → MGN replication → test boot → EC2 Mumbai → host retirement
AWS Transform for VMwareAWS Application Migration ServiceAmazon EC2AWS License ManagerAWS Site-to-Site VPN
03

Implementation approach

Weeks 1-3 · Pre-flightConsolidated 19 snapshot chains and fixed drivers on 31 VMs.
Weeks 4-6 · Test clusterConverted test and file servers with zero failed boots.
Weeks 7-14 · ProductionMoved SAP Business One, portal and EDI in three waves.
Weeks 15-16 · RetirementEvacuated six hosts before the renewal date.
04

Measured results

Annual virtualisation licence and support
INR 58 lakh renewal quote→INR 0 VMware; EC2 licence-included where needed
First-boot success after conversion
Not measured→126 of 128 VMs
EDI gateway cutover downtime
2-hour limit→70 minutes

Operational improvements

  • Test environments are started on demand for OEM audits rather than running all year.
  • Patching no longer waits on vSAN maintenance windows.
05

Cost considerations

EC2 and EBS run cost is about INR 4.1 lakh a month after right-sizing in week 6 of hypercare. The supplier skipped a vSAN node refresh estimated at INR 74 lakh. Savings Plans were bought for 70% of steady compute after 60 days.

06

Return on investment

ROI indicator

Avoiding the VCF renewal and the vSAN refresh outweighs AWS run cost by roughly INR 46 lakh a year. The migration fee was recovered in about eight months, before the next VMware anniversary would have fallen due.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.