Pumps and valves maker brings S/4HANA up in Delhi in 1 hour 48 minutes
Industrial pumps and valves manufacturer, 5 plants, 22 branch offices, about 1,300 SAP users · Google Cloud Mumbai (asia-south1) primary, Delhi (asia-south2) DR · 8 weeks
As-is situation
The manufacturer ran S/4HANA and BW on Google Cloud Mumbai with zonal HSR. DR relied on daily HANA backups copied to Cloud Storage in Delhi, with an estimated 14-hour recovery that had never been tested. A key oil and gas customer's vendor audit required a demonstrated ERP DR plan with RTO under 4 hours. Project orders for engineered pumps carried liquidated-damages clauses tied to dispatch dates.
- Untested DR with an estimated 14-hour RTO and a 24-hour RPO from daily backups.
- 74 interfaces, including bank host-to-host payments and an e-invoicing GSP, used IP addresses.
- Customer audit deadline was 10 weeks away.
Approach, tools and architecture
NTSPL added a tier-three HANA host in Delhi fed by multi-target async HSR from the Mumbai primary, sized at the next smaller M-series shape to save cost with a tested resize at takeover. Application servers and ASCS were built from Terraform in Delhi and kept stopped; /sapmnt and transports synced every 15 minutes. All 74 interfaces were moved to DNS names in Cloud DNS. A full drill ran on a Saturday with key users posting sales orders, goods receipts and an e-invoice.
Implementation approach
Measured results
Operational improvements
- Replication lag is shown on the operations dashboard and alerts at 5 minutes.
- The three interfaces that failed had certificate pinning issues, now covered in the drill checklist.
Cost considerations
The Delhi HANA host runs continuously under a committed use discount, and app servers stay stopped, so standby added about 32 percent to production infrastructure cost. Inter-region replication traffic was modest because HANA log shipping is compressed.
Return on investment
Meeting the customer audit kept the company on the approved vendor list for a framework contract worth an estimated INR 90 crore over three years. Even a small probability of losing that status outweighed the annual DR cost of roughly INR 60 lakh.