Ready-mix concrete firm sequences 3 SAP systems to Google Cloud around monsoon lows

Ready-mix concrete producer, 52 batching plants across 14 cities, about 1,100 SAP users · Google Cloud Mumbai (asia-south1) with DR in Delhi (asia-south2) · 12 weeks

Amazon Web Services
01

As-is situation

The company ran ECC on HANA, BW on HANA and PI/PO on an ageing on-prem HANA appliance whose support ended within the year. Batching plants pushed delivery tickets to SAP through PI every few minutes, and invoices were generated per pour for 6,000 active customer sites. Sales volume dropped by about 40 percent during monsoon months, but the original plan proposed moving all three systems in one October weekend, the start of construction peak.

  • All three systems were planned for one weekend, giving a 60-hour combined outage at peak season.
  • 52 batching plants depended on PI for ticket posting and had no offline process.
  • BW nightly loads depended on ECC delta queues that had to be emptied and restarted in sequence.
02

Approach, tools and architecture

NTSPL re-sequenced the move into three cutovers between late June and mid-August, the lowest-volume period. As the source was already on HANA, ECC and BW moved like-for-like using HANA system replication from the appliance to Google Cloud, followed by a short takeover. PI/PO moved first with a dual-running window to prove plant connectivity. A plant offline template for delivery tickets was created and tested. BW delta queues were drained and verified in the runbook before each ECC step.

PI/PO first → HSR from appliance to Google Cloud for ECC → BW after delta drain → takeover → Delhi DR enabled
SAP HANA system replicationCompute Engine M-seriesCloud InterconnectCloud StorageWorkload Manager for SAP
03

Implementation approach

Weeks 1-2 · Re-sequencingCalendar rebuilt around monsoon volume data and plant availability.
Weeks 3-6 · PI/PO movePI/PO migrated with dual-running for plant ticket interfaces.
Weeks 7-10 · ECC via HSRReplication established, two takeover rehearsals run, production takeover completed.
Weeks 11-12 · BW moveBW replicated and taken over after delta queues were drained.
04

Measured results

Longest single business outage
60 hours planned→6 hours for ECC takeover
Delivery tickets posted late after cutover
Forecast 9,000 tickets→1,240 tickets, cleared in 5 hours
BW load failures after migration
Not applicable→0

Operational improvements

  • Plant offline ticket templates are now part of the business continuity plan for any SAP outage.
  • PI/PO monitoring on cloud alerts plant IT directly when a batching plant stops posting.
05

Cost considerations

Running source and target in parallel for about 10 weeks added infrastructure cost, partly covered by retiring the appliance support contract early. Interconnect bandwidth was sized for HSR initial load and then reduced after cutover.

06

Return on investment

ROI indicator

Moving the outage out of peak season and cutting it to hours protected an indicative INR 6 to 8 crore of pour revenue that would have been at risk over a 60-hour October outage, against a planning engagement of roughly 35 consultant-days.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.