AWSPower transmission EPCEnergy, Utilities & Resources

Power transmission EPC fits a 4.6 TB S/4HANA conversion into a 40-hour window

Transmission line and substation EPC contractor, 60 active project sites, about 2,800 SAP users · AWS Asia Pacific (Mumbai) · 14 weeks from re-plan to go-live

Amazon Web Services
01

As-is situation

The EPC company ran ECC 6.0 EhP8 on Oracle with heavy use of Project System for 60 transmission and substation projects, and planned a brownfield conversion to S/4HANA on AWS. The database was 4.6 TB. Its first mock run with a previous partner had taken 71 hours, while management allowed 40 hours because site billing and milestone invoices to state utilities could not stop longer. Quarter-end milestone billing made the last two weeks of each quarter unusable for cutover.

  • First mock runtime was 71 hours against a 40-hour business window.
  • Project System tables and change documents made up 1.9 TB, concentrated in 15 large tables.
  • Only three weekends in the following six months avoided quarter-end billing and GST return dates.
02

Approach, tools and architecture

NTSPL re-planned using DMO with system move, exporting on-prem and importing on AWS over a 10 Gbps Direct Connect. Table splitting was benchmarked for the 15 largest tables, and change-document archiving reduced the database to 3.9 TB before mock 2. The downtime budget was split into 28 hours technical, 8 hours business validation and 4 hours contingency. Two mocks and a dress rehearsal ran on copies refreshed within three weeks. The runbook covered milestone-billing backlog entry for each project site.

Downtime budget 28+8+4 h → archiving → DMO with system move → Direct Connect transfer → import on EC2 High Memory → validation → go-live
SAP Software Update Manager DMO with system moveAWS Direct ConnectAmazon EC2 High Memory instancesAmazon S3AWS Launch Wizard for SAP
03

Implementation approach

Weeks 1-3 · Re-planDowntime budget agreed with the CFO and technique changed to DMO with system move.
Weeks 4-8 · Mock 2Archiving completed and mock 2 run with benchmarked table splits.
Weeks 9-12 · Mock 3 and dress rehearsalRunbook refined and dress rehearsal timed on the cutover clock.
Week 14 · Production cutoverCutover on a long weekend chosen to avoid quarter-end and GST dates.
04

Measured results

Technical migration runtime
71 hours at mock 1→26.5 hours at production
Total business downtime
Not achievable in 40 hours→37 hours
Database size migrated
4.6 TB→3.9 TB
Milestone invoices delayed by cutover
Forecast 140→0

Operational improvements

  • Project site teams re-entered weekend progress entries in 3 hours using a pre-built template.
  • The runbook format became the standard for later BW and PI/PO moves.
05

Cost considerations

Two extra mock runs added roughly 9 days of production-sized capacity on AWS, and Direct Connect was upgraded for the migration months. Archiving required 12 days of functional and Basis effort. Each cost was small compared with extending the outage into billing weeks.

06

Return on investment

ROI indicator

Staying within 40 hours protected about INR 210 crore of quarter-end milestone billing from slipping into the next quarter. The indicative benefit was interest saved on working capital and avoided liquidated-damages disputes, estimated at INR 1.4 crore.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.