Ball and roller bearings manufacturer for auto and industrial OEMs, 4 plants, export to 30 countries · Google Cloud Mumbai (asia-south1) · 8 weeks
As-is situation
The bearings maker was moving from on-prem appliances to Google Cloud. Its BW on HANA 7.5 ran as a 1+3 scale-out of 1 TB nodes plus a standby, purely because the 2016 appliances had a memory ceiling. BW held 3.1 TB of data, with nightly loads of OEM schedules, plant OEE and export shipment data. Cross-node joins slowed key planning queries and node-level failures had caused two failed overnight loads in the past year.
- Planning queries joining customer schedules with plant output took 70 to 90 seconds due to cross-node data movement.
- Five appliance nodes including standby had to be patched in sequence, making each HANA revision upgrade an 8-hour job.
- About 900 GB of BW data sat in ADSOs for product lines discontinued years earlier.
Approach, tools and architecture
NTSPL profiled BW objects and agreed with the planning team to archive inactive ADSOs through near-line style data archiving processes and delete obsolete PSA data. The remaining 2.2 TB was consolidated into a single scale-up HANA on an M-series machine with headroom for three years of forecast growth. Table redistribution was replaced by fiscal-year partitioning on the largest ADSOs. HSR in logreplay mode was designed to a second zone, and Fast Restart was enabled to shorten restarts after patching.
Implementation approach
Measured results
Operational improvements
- Patching follows the same scale-up runbook as S/4HANA, so the Basis team maintains one procedure.
- HSR takeover replaced the standby node model and was tested quarterly.
Cost considerations
One large M-series machine plus a secondary cost less than five scale-out nodes would have on cloud, and Hyperdisk throughput was sized once instead of per node. Archive files in Cloud Storage cost a few thousand rupees a month.
Return on investment
Consolidation reduced projected BW infrastructure cost by about 35 percent compared with a like-for-like scale-out on cloud, an indicative INR 55 lakh a year. Faster planning queries also shortened the weekly sales and operations planning cycle by half a day.