Specialty steel maker builds five S/4HANA tiers from code in 19 days
Alloy and stainless long-products producer, 2 melt shops, about 2,200 SAP users · Google Cloud Mumbai (asia-south1) · 19 days build, 6 weeks including handover
As-is situation
The steelmaker had approved a brownfield conversion from ECC on DB2 to S/4HANA and chosen Google Cloud. Its previous attempt at a sandbox had taken five weeks of manual VM builds, and the resulting host failed HANA storage checks because log and data shared one disk. Heat-number traceability and quality certificates depended on custom ABAP running in long batch jobs. The conversion partner needed five tiers ready before the first mock run, ten weeks away.
- A hand-built sandbox took 5 weeks and failed the HANA log latency KPI by a wide margin.
- Production HANA was sized at 2.8 TB, but no repeatable template existed for development, quality or pre-production.
- Batch jobs for heat traceability ran 3 to 4 hours nightly and were sensitive to app-to-database latency.
Approach, tools and architecture
NTSPL wrote Terraform modules for HANA, ASCS/ERS, application servers and Web Dispatcher, with one parameter file per tier. HANA used M-series machines with separate Hyperdisk Extreme for log and Hyperdisk Balanced for data and shared volumes. SLES for SAP images were hardened once and pinned. Application servers were placed in the same zone as HANA with compact placement where the machine type supported it. HCMT was run on every HANA host before handing over to the conversion partner, and Workload Manager evaluations were scheduled weekly.
Implementation approach
Measured results
Operational improvements
- Mock conversion copies are restored onto fresh hosts built from code, so each rehearsal starts from an identical platform.
- Weekly Workload Manager reports caught two OS parameter changes made outside the pipeline before they reached production.
Cost considerations
Non-production tiers were scheduled to stop overnight and on Sundays from the first week, keeping build-phase cloud spend about 45 percent below an always-on estimate. Production was built last, three weeks before the first mock, so it did not accrue idle cost during module development.
Return on investment
Delivering tiers five weeks earlier than the manual approach kept the conversion partner's mock-run schedule intact. NTSPL's indicative estimate is INR 70 to 90 lakh of avoided partner standby and programme delay, plus faster refreshes for every later test cycle.