Microsoft AzurePolymer and specialty plastics manufacturingManufacturing & Industrial

Polymer company runs one wave calendar for three plants and a head office

Engineering plastics compounder with 3 plants and 2,100 employees · Vadodara, Silvassa and Pune, India · 30 weeks

Amazon Web Services
01

As-is situation

The company had 286 servers across three plant server rooms and a head office. Each plant's IT lead ran its own vendor relationships and change calendar. SAP ECC was out of scope and stayed in an existing hosted contract, but 34 interfaces linked it to plant systems. Plant shutdown calendars differed, and two plants had quarterly maintenance shutdowns that were the only safe windows for production historians and lab systems. Nobody owned the overall calendar or the cross-site dependencies, and the 34 SAP interfaces were documented only in vendor emails.

  • Four separate change calendars and three local vendors.
  • 34 SAP interfaces had to be retested with every affected wave.
  • Historian and lab systems could move only during plant maintenance shutdowns.
02

Approach, tools and architecture

NTSPL set up one backlog, one intake gate and a single wave calendar that combined all four sites' freeze dates. Plant vendors joined squads using shared templates rather than their own methods. Waves were formed by dependency and site, with historian and lab systems placed in the two maintenance shutdown windows. An interface test pack for the 34 SAP links ran in every wave that touched them. Azure Migrate replicated servers into Central India, with batched replication per wave. Plant leads approved each wave.

Four site inventories → single backlog → combined freeze calendar → Azure Migrate waves → SAP interface test pack → Central India
Azure MigrateAzure Site RecoveryAzure MonitorAzure Update ManagerAzure Bastion
03

Implementation approach

Weeks 1-4 · Calendar and squadsCombined calendars and brought plant vendors into two squads.
Weeks 5-8 · PilotsMoved head office workloads first.
Weeks 9-30 · Plant wavesMoved plants in turn, using both shutdown windows for historians.
04

Measured results

Change calendars in use
4→1
SAP interface failures after waves
Not tracked→2 in 30 weeks, both fixed in hypercare
Servers migrated or retired
0 of 286→286 of 286

Operational improvements

  • Plant IT leads now share one operating model and templates.
  • The interface test pack is reused for SAP changes after migration.
05

Cost considerations

Bringing plant vendors into common squads avoided three separate migration contracts and duplicated tooling. Waiting for plant shutdowns stretched the timeline by about six weeks but avoided production risk. 31 servers were retired during intake because no owner claimed them.

06

Return on investment

ROI indicator

Closing three plant server rooms saves about INR 1.1 crore a year in AMCs, power and hardware refresh. The factory approach kept migration services about 30% below the sum of the three plant-level quotes received earlier.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.