AWSGlass manufacturingManufacturing & Industrial

Glass manufacturer restarts a stalled programme and moves 410 servers in 22 weeks

Float and container glass manufacturer with 4 plants · Gujarat and Rajasthan, India · 22 weeks

Amazon Web Services
01

As-is situation

A migration to AWS had started nine months earlier with a different partner. Only 48 of 458 servers had moved. Each wave was planned from scratch, app owners heard about cutovers days in advance, and firewall requests took two weeks each. The colocation contract had been extended twice at a premium. Four plants each ran their own MES-adjacent reporting servers, and furnace operations meant plant teams could only test on Tuesdays and Wednesdays. Leadership had lost confidence in every date offered.

  • 48 of 458 servers moved in nine months.
  • Firewall changes took about two weeks per request.
  • Plant app testers were available only two days a week.
02

Approach, tools and architecture

NTSPL rebuilt the programme as a factory. All workloads were loaded into one backlog, and a 12-point intake gate set readiness. Firewall rules were batched per wave and pre-approved against a standard pattern, cutting lead time to three days. Two squads ran fortnightly waves, each with a test cutover on Tuesday and production at the weekend. Application Migration Service groups mirrored the waves, and post-launch actions installed agents automatically. Decommissioning was part of wave closure. Every wave fed one weekly report.

Single backlog → 12-point intake gate → wave calendar → MGN application groups → Tuesday test cutover → weekend production → decommission
AWS Application Migration ServiceAWS Systems ManagerAWS Database Migration ServiceAmazon EC2AWS Control Tower
03

Implementation approach

Weeks 1-3 · Factory setupLoaded the backlog, set the gate and batched firewall patterns.
Weeks 4-7 · Pilot wavesMoved 36 servers in three waves and tuned templates.
Weeks 8-22 · Full velocityTwo squads moved the remaining servers with 48 retired.
04

Measured results

Servers migrated per month
About 5→About 75
Firewall request lead time
14 days→3 days
Wave rollback rate
Not tracked→3%

Operational improvements

  • Leadership receives a weekly forecast end date that held within two weeks.
  • Plant testers know their test slots three waves ahead.
05

Cost considerations

Ending the colo two months earlier than the revised forecast avoided about INR 54 lakh of extension fees. Per-server migration cost fell by about 40% after the pilot. Retiring 48 servers avoided their cloud run cost entirely.

06

Return on investment

ROI indicator

The restart cost was recovered through avoided colo extensions alone. Run cost savings against the old colo of about INR 1.6 crore a year now flow as planned in the original business case, which had been at risk.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.