Steel trader surrenders its colo cage 11 days early and drops INR 62 lakh a year

Flat and long steel trader, 14 stockyards, about INR 2,400 crore turnover · Raipur and Navi Mumbai, India · 28 weeks

Amazon Web Services
01

As-is situation

The trader ran 118 servers in a four-rack Navi Mumbai colo cage: a branch accounting cluster, a stockyard management app on SQL Server 2016, a weighbridge integration server, 9 TB of mill test certificates in a document system, and Veeam backup to an LTO-7 library. The renewal quote rose 16% per rack. Two storage controllers were six months from end of support, and the stockyard leased line carried a 90-day exit clause buried in a 2021 renewal that nobody in IT had seen.

  • Renewal 16% higher per rack, with a hard date 30 weeks out.
  • SQL Server 2016 left extended support in July 2026 with no upgrade plan.
  • 27 devices, including weighbridge serial-to-IP converters and a dongle hub, had no owner.
02

Approach, tools and architecture

A two-day walk-down tagged all 27 orphan devices; the dongle hub was replaced by a vendor network licence and the serial converters moved to the Raipur stockyard. Azure Migrate moved servers to Central India in seven rack-aligned waves, with South India holding recovery copies. The stockyard database was upgraded to SQL Server 2022 during its wave rather than as a separate project. Certificates moved to Azure Files, and three years of tapes were restored to archive-tier Blob storage before the library shipped out.

Walk-down → contract register → Azure Migrate → dual VPN → Central India landing zone → rack-dark gate → surrender
Azure MigrateAzure VPN GatewayAzure FilesAzure Blob StorageAzure Site Recovery
03

Implementation approach

Weeks 1-4 · Walk-downTagged every rack unit and logged 19 contracts.
Weeks 5-8 · PilotMoved 14 test and reporting servers in two waves.
Weeks 9-24 · Rack wavesFive waves darkened all four racks, avoiding the Diwali weekend.
Weeks 25-28 · SurrenderWiped 212 disks and handed back the cage.
04

Measured results

Annual facility and AMC cost
INR 1.41 crore→INR 79 lakh including Azure
Cage surrender
Deadline week 30→Week 28, 11 days early
Unowned devices
27→0

Operational improvements

  • Branches open mill test certificates in under 3 seconds instead of over a WAN share.
  • Night-time tape rotation by a colo technician was dropped.
05

Cost considerations

The largest one-off cost was 14 weeks of double running at about INR 6.5 lakh a month. Releasing the leased line after wave 4 instead of at the end saved three months of rental. Reservations were bought only after 60 days of usage data.

06

Return on investment

ROI indicator

Against the renewal quote plus the avoided storage controller refresh, the trader saves about INR 62 lakh a year. Migration fees and the double-running months were recovered in roughly 15 months, inside the same financial year's budget review.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.