Private university clears its campus server room before a new academic block is built
Multi-faculty university, 18,000 students and 1,400 staff · Pune, India · 26 weeks
As-is situation
The server room sat in a building due for demolition to make way for a new academic block. It held 164 VMs on three ageing VMware clusters, a physical Moodle cluster, an Oracle-based ERP for fees and HR, on-prem LDAP feeding campus Wi-Fi authentication, and a 60 TB research NAS. Cooling had failed twice one summer, pushing result processing onto a single host. The contractor needed the room empty in 26 weeks, and end-semester exams froze four of those weeks.
- Exam freezes left 22 usable weeks.
- Wi-Fi depended on on-prem LDAP, so a slip would lock out 18,000 students.
- The research NAS held data for 40 grant-funded projects with mandated retention.
Approach, tools and architecture
NTSPL moved the estate to AWS Mumbai, with Hyderabad holding backups. Application Migration Service rehosted 151 VMs in six waves; 13 were retired after owners confirmed no use. Directory and RADIUS moved first to EC2 over dual VPN, with Wi-Fi failover tested during a holiday before any other wave. DataSync moved the research NAS into FSx for NetApp ONTAP, preserving per-project quotas and snapshots. An edge rack in the library building now holds only campus core switching and the Wi-Fi controllers.
Implementation approach
Measured results
Operational improvements
- Research storage is billed per project, so grant budgets carry their own cost.
- Moodle capacity scales up for admission season and back down afterwards.
Cost considerations
The university avoided about INR 2.1 crore in replacement servers, storage and a new server room fit-out. ONTAP deduplication cut billed research storage to about 38 TB, and dual VPN replaced Direct Connect because initial data was under 75 TB.
Return on investment
Annual AWS run cost including backup is about INR 96 lakh against INR 1.18 crore for the old room's power, AMCs and hardware refresh reserve. The avoided fit-out of a new server room alone exceeded total migration spend, so payback was immediate.