Manufacturer of fans, appliances and lighting, 4 plants, 12,000 dealers, INR 6,500 crore revenue · Northern and Western India · 28 weeks

Amazon Web Services
01

As-is situation

SAP ECC 6.0 EHP6 ran on Oracle 12c on IBM Power servers in a co-located data centre, with a 4.2 TB database. The company ran SD, MM, PP, FI-CO and a dealer portal connected through PI. Month-end close took 6 working days, partly due to long-running batch jobs, and the dealer schemes module had 1,400 custom objects. ECC mainstream maintenance was ending in 2027, the Power servers needed renewal, and the CFO wanted S/4HANA Finance features for faster close. The IT team had one attempt at an S/4 readiness check that showed 380 simplification items.

  • 4.2 TB Oracle database on ageing IBM Power hardware
  • 380 simplification items and 1,400 custom objects in the dealer schemes area
  • Month-end close taking 6 working days
  • Business downtime window limited to 48 hours over a long weekend
02

Selected Microsoft Azure services and architecture

NTSPL handled the Azure platform and migration while the SI partner led functional conversion. Azure Center for SAP solutions deployed S/4HANA infrastructure for sandbox, development, QA and production, with production HANA on a certified M-series VM sized at 3 TiB after data archiving and Unicode compression estimates. HANA data and log sit on Azure NetApp Files to use snapshots for frequent system copies during testing. The conversion used SUM with DMO directly from Oracle to HANA on Azure, with a downtime-optimized approach. Zonal HSR provides HA, and asynchronous HSR to South India provides DR.

Plant, dealer and finance users → ExpressRoute and Application Gateway for Fiori → SAP Web Dispatcher → S/4HANA application servers → HANA on M-series with ANF and zonal HSR → async HSR to South India
Azure Center for SAP solutionsAzure M-series VMsAzure NetApp FilesAzure Backup for SAP HANAAzure ExpressRouteAzure Monitor for SAP solutions
03

Implementation approach

Weeks 1-6 · Platform and sandboxBuilt the SAP landing zone and ExpressRoute, deployed a sandbox via Azure Center for SAP solutions and ran a first DMO conversion of a copy.
Weeks 7-20 · Remediation and testingSI partner remediated custom code and simplification items; NTSPL refreshed QA from ANF snapshots weekly for test cycles.
Weeks 21-26 · Dress rehearsalsRan three full DMO rehearsals, reducing technical downtime from 61 hours to 31 hours.
Weeks 27-28 · CutoverCompleted the conversion over a long weekend, with hypercare support from both teams for 4 weeks.
04

Measured results

Month-end close
6 working days→3 working days
Technical downtime for conversion
61 hours (first rehearsal)→31 hours (final cutover)
QA system refresh time
About 3 days→About 4 hours with ANF snapshots
Key batch job runtime (dealer scheme settlement)
9 hours→1.5 hours

Operational improvements

  • Test cycles use fresh QA copies from ANF snapshots instead of waiting days for refreshes
  • Additional application servers are started for month-end batch and stopped afterwards
  • Oracle database administration and IBM Power hardware support are no longer required
05

Cost considerations

ANF cost more per TiB than Premium SSD v2 but saved weeks of test-cycle time through snapshots, which the programme valued more. Non-production systems run on a snooze schedule outside project hours. Production reservations were purchased only after hypercare confirmed the HANA size. Oracle licence savings offset part of the Azure spend.

06

Return on investment

ROI indicator

Indicatively, avoiding the Power server and Oracle renewal saves INR 3 to 4 crore over 5 years, and a 3-day faster close frees finance capacity. The company estimates combined infrastructure and process benefits pay back the platform portion of the programme within 3 years.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.