AWSGlass bottlesMedia, Gaming & Entertainment

Glass bottle maker proves SAP failover in 18 tests before its furnace relining shutdown

Container glass manufacturer for beverages and pharma, 3 furnaces running 24x7, about 700 SAP users · AWS Asia Pacific (Hyderabad) · 3 weeks

Amazon Web Services
01

As-is situation

The glass maker had moved S/4HANA to AWS Hyderabad with a Pacemaker cluster built by a previous partner. Furnaces run continuously, and SAP drives batch weighing instructions, quality release and dispatch. The cluster had never been tested. During a HANA process crash, the overlay IP failed to move because the route table permission had been removed during an IAM cleanup, and production stopped for 52 minutes on a night shift. Auditors for a multinational beverage customer asked for failover evidence.

  • One failed takeover had caused a 52-minute outage because of a missing route-table permission.
  • No test catalogue or timings existed, and the cluster configuration was not under version control.
  • Fencing timeouts were set below the EC2 stop time, risking failed fences.
02

Approach, tools and architecture

NTSPL audited the cluster against SUSE and AWS reference guides, restored least-privilege IAM permissions for route table updates and EC2 stop and start, and raised fencing timeouts. Cluster configuration was exported and stored in Git. An 18-case test catalogue covered HANA crash, node crash, network isolation, ASCS kill, EFS unreachability and planned maintenance. Tests ran in quality, then in production in two windows scheduled with the plant ahead of the planned furnace relining shutdown, when demand was lowest.

HANA primary AZ-a → HSR syncmem → secondary AZ-b → fence_aws → overlay IP route update → ASCS/ERS cluster → EFS /sapmnt
Amazon EC2 R and X family instancesOverlay IP with VPC route tablesfence_awsAmazon EFSAWS Systems ManagerAmazon CloudWatch
03

Implementation approach

Week 1 · Cluster auditConfiguration compared with reference guides and IAM, timeouts and probes corrected.
Week 2 · Quality testingAll 18 cases run in quality with timings recorded.
Week 3 · Production testingTwelve production cases run in two windows with plant supervisors on call.
04

Measured results

Failure cases passing
Untested→18 of 18 in quality, 12 of 12 in production
Measured HANA takeover time
Failed after 52 minutes manual recovery→3 min 35 s
Cluster configuration changes outside version control
Unknown→0, checked weekly

Operational improvements

  • An IAM change-review step now flags any edit to cluster role permissions before it is applied.
  • The customer audit closed with the signed failover evidence pack as the main artefact.
05

Cost considerations

No new infrastructure was needed; the effort was 16 consultant-days of audit and testing. Production test windows were planned to avoid furnace pull rate changes, which had no direct cloud cost but needed plant coordination.

06

Return on investment

ROI indicator

A night-shift SAP stop delays quality release and dispatch of about 180 tonnes of bottles an hour. Preventing one repeat 52-minute outage avoids an indicative INR 35 lakh of delayed dispatch and potential penalties, many times the audit cost.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.