Fertilizer co-operative finds a non-Unicode blocker 9 months before its Azure move
Multi-state fertilizer co-operative, 3 urea and complex fertilizer plants, about 3,500 SAP users across 28 marketing offices · Azure Central India (Pune) · 6 weeks
As-is situation
The co-operative ran ECC 6.0 EhP6 on SQL Server 2012 and Windows Server 2012 R2, with a separate non-Unicode HR and payroll system from 2008 that handled 14,000 employees and retirees. Subsidy claim data for the fertilizer subsidy portal flowed through custom file interfaces. Azure had been chosen and a 7-month migration window approved, but the extended security updates for Windows Server 2012 were ending in October 2026 and the plan assumed a single like-for-like move.
- The 2008 HR system used a non-Unicode code page and could not move to HANA or S/4HANA without conversion.
- Subsidy-claim and dealer-sales file interfaces relied on 23 Windows scheduled tasks on two application servers that were not in any document.
- A third-party payroll add-on for co-operative-specific deductions had no published support for the target NetWeaver release.
Approach, tools and architecture
NTSPL inventoried all six production and twelve non-production systems, ran SAP Readiness Check on ECC and confirmed the HR system's code page through system tables. Because HR was 1.4 TB with a single code page, Unicode conversion was combined with its database migration to HANA, but scheduled as a separate weekend eight weeks before the ECC move. The Windows scheduled tasks were exported and each mapped to an Azure-hosted equivalent. The payroll add-on vendor confirmed support only after an upgrade, so the upgrade was added as a pre-migration task.
Implementation approach
Measured results
Operational improvements
- Subsidy-claim interfaces now have named owners and runbooks, so failures are triaged by the right team rather than by Basis.
- OS and database support dates for every system are tracked in one register, which the IT committee reviews quarterly.
Cost considerations
The assessment needed 32 consultant-days. The Unicode conversion added a separate migration weekend and about 18 days of Basis effort. The add-on upgrade was a vendor charge outside NTSPL's scope. Splitting downtime avoided extending the fertilizer dispatch freeze during the rabi season.
Return on investment
Finding the Unicode blocker during assessment instead of during the first mock migration avoided an estimated 6 to 8 weeks of programme delay. At the programme's monthly run rate of team and dual-running costs, that was worth roughly INR 1.2 crore.