Two-wheeler OEM cuts sized HANA memory from 6 TB to 3.4 TB before buying capacity

Motorcycle and scooter manufacturer, 4 assembly plants, 1,100 dealers, about 9,000 SAP users · AWS Asia Pacific (Mumbai) · 5 weeks

Amazon Web Services
01

As-is situation

The OEM ran ECC 6.0 EhP7 on Oracle 12c over IBM Power servers due for refresh in 14 months, plus BW 7.4 and PI 7.5. Production ECC held 11.2 TB on disk. Two partner quotes proposed 6 TB and 4 TB HANA instances on AWS, a gap worth several crore over three years. Nobody had a list of the dealer-portal, vendor-schedule and plant-MES interfaces, and the S/4HANA conversion was planned straight after the move.

  • Two sizing quotes for the same ECC system differed by 2 TB of HANA memory, with no evidence trail behind either.
  • Change documents, IDoc and application log tables made up 3.6 TB of the 11.2 TB database and had never been archived.
  • An estimated 180 interfaces existed, but only 64 were documented, mostly from the original 2012 rollout.
02

Approach, tools and architecture

NTSPL ran the HANA sizing report on production ECC twice: as-is, and after simulated archiving of change documents older than three years, IDocs older than 90 days and application logs older than 30 days. ST03N data from 13 months, including March close and the festive dispatch peak, was converted to SAPS for app servers. SAP Readiness Check flagged 412 simplification items, of which 61 were relevant. Interface exports from SM59, WE20 and SOAMANAGER plus a code scan for hard-coded FTP paths produced the register. Sizing was mapped to certified EC2 High Memory and X-family types in Mumbai.

HANA sizing report x2 → ST03N 13-month peaks → Readiness Check → interface exports + code scan → readiness register → certified EC2 mapping
SAP Readiness Check for SAP S/4HANAHANA sizing reportABAP Test CockpitAmazon EC2 High Memory instancesAWS Well-Architected SAP Lens
03

Implementation approach

Week 1 · Access and collectorsRead-only technical users created and Readiness Check collectors applied through SAP Notes on production.
Weeks 2-3 · Sizing and interfacesTwo sizing runs, SAPS conversion from workload history and interface exports reconciled with plant IT.
Weeks 3-4 · Compatibility reviewSimplification items triaged with finance and logistics leads, and three add-on vendors asked for written support statements.
Week 5 · Register sign-offBlocker list, sizing sheet and housekeeping plan accepted by the CIO and Basis lead.
04

Measured results

Production HANA memory sized
6 TB and 4 TB conflicting quotes→3.4 TB after agreed archiving
Interfaces documented with owner
64→187
Add-ons with confirmed S/4HANA support
Unknown for 11 add-ons→8 confirmed, 2 replaced by standard, 1 to be retired
Custom objects in remediation scope
5,240→2,310 after usage-based retirement

Operational improvements

  • Archiving for change documents and IDocs now runs as monthly background jobs, keeping HANA growth predictable after migration.
  • The interface register became the master list used by the network team to plan Direct Connect routes and firewall rules.
05

Cost considerations

The assessment took 38 consultant-days. Archiving needed SARA configuration and two weekends of jobs before migration. Moving from a 6 TB to a 3.4 TB certified instance class reduced the expected three-year compute commitment by roughly 40 percent, which was the main input to the AWS commitment negotiation.

06

Return on investment

ROI indicator

Indicatively, the difference between the higher quote and the evidence-based size was worth about INR 3.1 crore over three years of reserved capacity. Retiring 2,930 unused custom objects also removed an estimated 260 developer-days from the conversion budget.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.