FMCG company replaces a ₹6.2 crore refresh with an AWS case paying back in 26 months

Packaged-foods company, ₹2,400 crore revenue, 4 plants, 1,800 distributors · Indore head office, plants in Madhya Pradesh and Gujarat · 5 weeks

Amazon Web Services
01

As-is situation

The company ran 236 VMs and 30 physical servers in an Indore data centre it owned, with DR in a rented rack in Ahmedabad. A storage array and two blade chassis were end-of-support, and the refresh quote was ₹6.2 crore. IT had produced a cloud estimate showing 45 percent savings, but finance rejected it: it priced on-demand rates, left out dual running and ignored that the Ahmedabad rack contract ran 30 more months. The CFO asked for a model the audit committee could check.

  • The first estimate omitted ₹1.1 crore of migration labour and dual running
  • Power, AMC and the DR rack were missing from the on-premises side, worth ₹96 lakh a year
  • Distributor-management peaks in festive months made steady-state commitment levels uncertain
02

Approach, tools and architecture

NTSPL rebuilt both stacks from invoices and Migration Evaluator utilisation data. The on-premises side, including power at measured load, AMC escalation, the DR rack and staff time, was signed off by finance first. AWS costs used Mumbai pricing with Hyderabad for DR in pilot-light form, Compute Savings Plans at 50 percent coverage in year one and 70 percent from year two, and festive peaks on on-demand. Dual running was modelled wave by wave against the rack contract's exit date.

Invoices + Migration Evaluator → finance-signed on-prem stack → AWS Mumbai/Hyderabad stack → Savings Plans scenarios → NPV board pack
Migration EvaluatorAWS Pricing CalculatorCompute Savings PlansAWS Elastic Disaster Recovery (modelled)Excel model with actuals column
03

Implementation approach

Weeks 1-2 · EvidenceInvoices, power readings and contract dates gathered with the finance controller.
Weeks 3-4 · ModellingBoth stacks, dual running and three commitment scenarios built.
Week 5 · Audit committeeBoard pack presented with live model and assumption register.
04

Measured results

Five-year on-premises cost
₹9.1 crore in IT's estimate→₹13.4 crore fully loaded
Five-year AWS cost incl. one-off
₹5.0 crore claimed→₹10.2 crore modelled
Payback period
Not calculated→26 months

Operational improvements

  • Monthly actuals-versus-model review set up between IT and finance
  • Savings Plans purchases tied to a quarterly coverage review
05

Cost considerations

The engagement took 21 consultant days. The model's honest savings, about 24 percent over five years, were smaller than IT's original claim, which is why the audit committee accepted it.

06

Return on investment

ROI indicator

Five-year saving of about ₹3.2 crore, with NPV positive at the company's 12 percent hurdle rate and the ₹6.2 crore refresh avoided. Approval came in one cycle after the first proposal had been rejected.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.