FMCG company replaces a ₹6.2 crore refresh with an AWS case paying back in 26 months
Packaged-foods company, ₹2,400 crore revenue, 4 plants, 1,800 distributors · Indore head office, plants in Madhya Pradesh and Gujarat · 5 weeks
As-is situation
The company ran 236 VMs and 30 physical servers in an Indore data centre it owned, with DR in a rented rack in Ahmedabad. A storage array and two blade chassis were end-of-support, and the refresh quote was ₹6.2 crore. IT had produced a cloud estimate showing 45 percent savings, but finance rejected it: it priced on-demand rates, left out dual running and ignored that the Ahmedabad rack contract ran 30 more months. The CFO asked for a model the audit committee could check.
- The first estimate omitted ₹1.1 crore of migration labour and dual running
- Power, AMC and the DR rack were missing from the on-premises side, worth ₹96 lakh a year
- Distributor-management peaks in festive months made steady-state commitment levels uncertain
Approach, tools and architecture
NTSPL rebuilt both stacks from invoices and Migration Evaluator utilisation data. The on-premises side, including power at measured load, AMC escalation, the DR rack and staff time, was signed off by finance first. AWS costs used Mumbai pricing with Hyderabad for DR in pilot-light form, Compute Savings Plans at 50 percent coverage in year one and 70 percent from year two, and festive peaks on on-demand. Dual running was modelled wave by wave against the rack contract's exit date.
Implementation approach
Measured results
Operational improvements
- Monthly actuals-versus-model review set up between IT and finance
- Savings Plans purchases tied to a quarterly coverage review
Cost considerations
The engagement took 21 consultant days. The model's honest savings, about 24 percent over five years, were smaller than IT's original claim, which is why the audit committee accepted it.
Return on investment
Five-year saving of about ₹3.2 crore, with NPV positive at the company's 12 percent hurdle rate and the ₹6.2 crore refresh avoided. Approval came in one cycle after the first proposal had been rejected.