India’s Leading Domain & Web Hosting Provider
Chemical plant writes MES recovery runbooks that operators and IT can both execute
Single-site specialty chemicals plant, 3 production blocks, batch MES and historian connected to Google Cloud · Google Cloud Mumbai, recovery in Delhi; plant edge servers on site · 7 weeks
As-is situation
The plant ran batch recipes, electronic batch records and material genealogy in an MES whose application and database tiers had moved to Compute Engine and Cloud SQL in Mumbai, with edge servers on site buffering data from the DCS and historian. Backup and DR Service protected the VMs, with a Delhi copy. When a misapplied firewall change cut the plant off from Mumbai for three hours, operators switched to paper batch records, and reconciling them back into the MES took four days. IT discovered the edge buffers held only 90 minutes of data. Nobody had written down how operators and IT should act together during an MES outage.
- No defined point at which operators should switch to paper or pause batches
- Edge buffers held 90 minutes of data, so longer outages lost historian records
- Restoring MES in Delhi had never been tried, and the plant's network path to Delhi was unconfigured
Approach, tools and architecture
NTSPL wrote four runbooks with plant operations, QA and IT: MES outage response for operators (with triggers at 15, 60 and 120 minutes), MES recovery in Delhi for IT, edge buffer management, and paper-to-MES reconciliation for QA. Edge buffer capacity was raised to 12 hours. The Delhi recovery was automated as a Workflows sequence that restored VMs from Backup and DR Service, promoted a Cloud SQL cross-region replica, applied Terraform for networking and switched the edge servers' target through an internal DNS change. The plant's SD-WAN gained a pre-configured path to Delhi. Each runbook began with the safety and quality hold rules QA required.
Implementation approach
Measured results
Operational improvements
- Shift in-charges have laminated operator runbooks at each block control room
- Firewall changes affecting the plant path now require a rollback step and MES connectivity check
Cost considerations
Enlarging edge buffers required additional on-site storage worth about INR 3.5 lakh. The Cloud SQL replica in Delhi adds about INR 48,000 a month. Workflows and Cloud Build executions during drills cost negligible amounts. No new licences were needed.
Return on investment
The previous three-hour outage cost four days of QA time and delayed release of six batches. Faster reconciliation and recovery protect batch release schedules, which drive shipments to export customers with fixed delivery windows. QA effort was also cut.