AWSCement manufacturingManufacturing & Industrial

Cement manufacturer adds HANA high availability and Hyderabad DR to S/4HANA on AWS

Cement producer, 6 integrated plants and 5 grinding units, about 2,800 SAP users · Central and Southern India · 11 weeks

Amazon Web Services
01

As-is situation

S/4HANA had been running on AWS Mumbai for two years, but in a single Availability Zone, with a 2.6 TB HANA on one X2iedn instance and no HANA System Replication. Backups ran nightly to EBS and were then copied to S3 with scripts. Dispatch, weighbridge and truck-sequencing at all plants depended on SAP; when an instance retirement notice forced an unplanned restart, dispatches stopped for 3 hours and about 1,400 trucks queued across plants. The audit committee asked for a recovery design that survives an AZ outage and a regional event, with drills recorded.

  • Single-AZ HANA of 2.6 TB with no replication; recovery from backup estimated at 10 to 14 hours
  • Plant dispatch fully dependent on SAP, about 1,400 trucks stopped in a 3-hour outage
  • Backups scripted to S3 with no verification, and log backups only every 30 minutes
  • Board requirement for regional DR within India with documented drills
02

Selected AWS services and architecture

NTSPL added a HANA secondary on a matching X2iedn instance in a second Mumbai AZ with HSR SYNCMEM and Pacemaker on SLES for SAP, using the SAPHanaSR resource agents, EC2 API fencing and an overlay IP. ASCS/ERS moved to an ENSA2 Pacemaker cluster with /sapmnt on Amazon EFS. For regional DR, a third HANA tier in Hyderabad received HSR ASYNC on a smaller instance with column preload disabled, resized during takeover. Elastic Disaster Recovery replicated application servers and the weighbridge interface hosts. Scripted backups were replaced by the AWS Backint Agent with 10-minute log backups to an Object Lock bucket replicated to Hyderabad.

Plant dispatch and weighbridge systems → Direct Connect → S/4HANA application servers in two Mumbai AZs → HANA primary X2iedn with HSR SYNCMEM to AZ-b secondary (Pacemaker, overlay IP) → HSR ASYNC to resizable Hyderabad tier → Backint to Object Lock S3
Amazon EC2 X2iednSUSE Linux Enterprise Server for SAP with PacemakerAWS Backint AgentAWS Elastic Disaster RecoveryAmazon EFSAmazon S3 Object Lock
03

Implementation approach

Weeks 1-2 · Design and capacity checkConfirmed instance availability in both Mumbai AZs and Hyderabad, and designed the three-tier HSR topology.
Weeks 3-6 · HA buildBuilt the secondary, completed initial HSR sync over a weekend and configured Pacemaker clusters for HANA and ASCS/ERS.
Weeks 7-9 · DR tier and backupsBuilt the Hyderabad tier, Elastic Disaster Recovery replication and the Backint backup design.
Weeks 10-11 · Takeover tests and drillRan AZ takeover tests during a planned window and a full Hyderabad DR drill with plant dispatch validation.
04

Measured results

Recovery from instance or AZ failure
10-14 hours (restore)→About 5 minutes (measured takeover)
Regional DR recovery time
None→About 95 minutes in drill
HANA log backup interval (RPO from backup)
30 minutes→10 minutes
Recorded HA and DR drills per year
0→2 AZ tests + 2 regional drills

Operational improvements

  • Instance retirement and OS patching now use planned HANA takeovers with minutes of impact instead of hours
  • Plant IT teams have a printed dispatch fallback card that matches the measured DR timeline
  • CloudWatch alarms on HSR status alert the Basis team the moment replication falls out of sync
05

Cost considerations

The second X2iedn in Mumbai doubled production HANA instance cost and was covered by a three-year Savings Plan. The Hyderabad tier used a smaller instance with preload disabled, trading a longer regional RTO for a large standby saving. Inter-Region transfer for HSR ASYNC stayed modest because, after the initial full sync, mainly log and delta traffic crosses Regions.

06

Return on investment

ROI indicator

A 3-hour dispatch stoppage cost the company an indicative INR 1.5 to 2 crore in delayed despatches and demurrage. The HA and DR additions cost about INR 6 to 8 lakh per month, so avoiding one such outage every couple of years covers the spend, before counting regional DR.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.