Auto-ancillary maker converts ECC to S/4HANA on AWS inside a 48-hour downtime window

Tier-1 auto-ancillary manufacturer, 9 plants, about INR 3,200 crore revenue · Western and Southern India · 24 weeks

Amazon Web Services
01

As-is situation

ECC 6.0 EHP7 ran on Oracle 12c on ageing Unix servers in the company's Pune data centre, with a 4.2 TB database, 1,100 named users and JIT and sequencing interfaces to four vehicle OEMs through EDI. The hardware vendor's support ended in 14 months, and the replacement quote for new servers plus a HANA appliance and DR site was about INR 6 crore. MRP runs took 7.5 hours overnight and often overlapped first-shift production. OEM contracts allowed no more than 48 hours of SAP downtime, which had to fall inside a planned annual plant shutdown.

  • 4.2 TB Oracle database, 1,100 users and OEM JIT interfaces with strict downtime limits
  • Hardware support ending in 14 months; refresh quote about INR 6 crore
  • MRP runtime of 7.5 hours overlapping the first shift
  • Maximum business downtime of 48 hours, inside the annual shutdown
02

Selected AWS services and architecture

NTSPL and the client's SAP functional partner ran a brownfield system conversion using SUM DMO with system move, migrating from Oracle in Pune to S/4HANA on AWS Mumbai in one downtime window. Archiving and data volume management reduced the source to 3.1 TB, and the resulting HANA footprint was about 1.3 TB, placed on an X2idn instance with headroom. Launch Wizard for SAP built production with HANA HSR SYNC across two Mumbai AZs under Pacemaker and ASCS/ERS in a separate cluster. Data volumes used striped gp3 and logs used io2 Block Express. Backint streamed backups to S3 with replication to Hyderabad.

Plant users and OEM EDI → Direct Connect → SAP Web Dispatcher → S/4HANA application servers in two Mumbai AZs → HANA primary on X2idn with HSR SYNC to AZ-b secondary (Pacemaker) → Backint to S3 → replication to Hyderabad
Amazon EC2 X2idnAmazon EBS gp3 and io2 Block ExpressAWS Launch Wizard for SAPAWS Backint AgentAWS Direct ConnectAmazon EFS
03

Implementation approach

Weeks 1-5 · Sizing and readinessRan SAP readiness checks, simplification item analysis and archiving, and sized HANA at 1.3 TB plus growth.
Weeks 6-12 · Build and first mockBuilt sandbox and QA with Launch Wizard, completed the first DMO mock in 61 hours and tuned parallelism.
Weeks 13-20 · Testing and second mockRan integration tests with OEM EDI partners and a second mock at 36 hours of technical downtime.
Weeks 21-24 · Cutover and hypercareCut over during the annual shutdown in 38 hours end to end, then ran four weeks of hypercare.
04

Measured results

Business downtime at cutover
Limit 48 hours→38 hours
Nightly MRP runtime
7.5 hours→1.8 hours with MRP Live
Database footprint
4.2 TB Oracle→About 1.3 TB HANA in memory
HA failover tested before go-live
None→HANA takeover in about 4 minutes

Operational improvements

  • MRP Live completes before first shift, so plant planners start the day with current requirements
  • Basis team patches HANA with a planned takeover to the secondary, cutting maintenance downtime to minutes
  • Sandbox systems are cloned from production backups in hours for testing OEM interface changes
05

Cost considerations

Production HANA and central services were placed on three-year Instance Savings Plans after hypercare confirmed sizing. Non-production systems run on Systems Manager schedules, about 60 hours a week. io2 Block Express was limited to log volumes. SAP licences moved under existing agreements; the S/4HANA licence conversion was handled separately with SAP.

06

Return on investment

ROI indicator

Avoiding the INR 6 crore hardware and DR refresh, against an indicative AWS run cost of INR 14 to 18 lakh per month with three-year commitments, gives a comparable five-year infrastructure cost with HA and DR included. Faster MRP removed first-shift planning delays, which the plants valued at INR 1 to 1.5 crore a year.

Illustrative scenario: a composite based on typical NTSPL engagement patterns for this industry and service. It does not describe a named customer. The figures are indicative, and actual results depend on the workload, its scale and the commercial terms.