SAP Cloud Assessment: RISE, Hyperscaler IaaS or Stay Before 2027

Quick answer

An SAP cloud assessment is a strategic decision study on whether, when and how an SAP landscape should move to cloud: RISE with SAP, S/4HANA on hyperscaler IaaS under your own licences, or staying on-premises for now, timed against ECC 6.0 mainstream maintenance ending in 2027. NTSPL compares cost, risk, control and timing for CIOs and CFOs facing that decision.

Delivered on

AWS: 4 native toolsMicrosoft Azure: 4 native toolsGoogle Cloud: 4 native tools

In scope

Landscape baselineOption definitionFive-year cost comparisonRisk and controlTiming and roadmap
Cloud Assessment · SAP Cloud Assessment

Three Clocks Every ECC Customer Is Running Against

Indian SAP customers on ECC face three overlapping clocks: mainstream maintenance ending in December 2027, a hardware refresh, and SAP's commercial push toward RISE. Decisions are often made on whichever proposal arrives first. A RISE quote compares a subscription against hardware only; an IaaS quote ignores Basis effort and conversion risk; staying on ECC ignores extended maintenance premiums and a thinning partner pool.

NTSPL frames the decision with four options: stay on ECC on-premises, move ECC to IaaS now and convert later, convert to S/4HANA on IaaS, or adopt RISE with SAP. Each is scored on five-year cost, conversion risk, operational control, contract flexibility and timing against 2027. The output is a recommendation with a business case, not a technical sizing, which follows once the direction is chosen.

When SAP Leadership Needs a Strategic Decision Study

Signals you need SAP Cloud Assessment

  • ECC 6.0 in production with no approved plan for the end of mainstream maintenance in 2027
  • A RISE with SAP proposal is on the table and finance cannot compare it with alternatives
  • SAP hardware or HANA appliances reach end of support within 18 months
  • Group companies run separate SAP instances and leadership is weighing consolidation

When to choose something else

  • The move and target are already decided and you need SAPS and HANA memory sizing, OS/DB checks and interface analysis: that is a technical readiness assessment.
  • SAP is already on S/4HANA in cloud and the concern is cost: that is SAP FinOps.

Questions the SAP Decision Study Answers

01

Landscape baseline

Systems, versions, database, size, custom code volume, add-ons, interfaces and current hosting and support contracts.

02

Option definition

Four options defined with what SAP, the hyperscaler, NTSPL or your team owns in each.

03

Five-year cost comparison

Licences, subscription, infrastructure, Basis and AMS, conversion project and extended maintenance premiums.

04

Risk and control

Conversion complexity from SAP Readiness Check, custom code, contract lock-in and operational control per option.

05

Timing and roadmap

Sequence against 2027, fiscal year-end, audits and business peaks, with go/no-go points.

Interactive framework · Four-Option SAP Strategic Decision Model

Four-Option SAP Decision Model

Four-Option SAP Strategic Decision Model

A landscape baseline and SAP Readiness Check results define conversion complexity. Four options are costed and scored on risk, control and timing, producing a recommended path and a board business case.

Baseline
Options
Evaluation
Decision
Interactive reference architecture

Select any component

Four-Option SAP Strategic Decision Model: click any of its 7 components to see its role and the design choice NTSPL makes for it, or trace the 7-step primary path.

Landscape and contract baseline → SAP Readiness Check results → Four defined options → Five-year cost model → Risk and control scoring → 2027 timing model → Recommended path and business case

SAP Hosting Options on AWS, Azure and Google Cloud

AWS

IaaS options on AWS are costed on SAP-certified instances in Mumbai with Hyderabad DR; RISE on AWS is compared on the same scope.

SAP-certified Amazon EC2 instancesAWS Launch Wizard for SAPAWS Backint AgentRISE with SAP on AWS
Microsoft Azure

Azure options are costed in Central India with South India DR, and Azure Center for SAP solutions reduces Basis deployment effort in the IaaS scenarios.

Azure Center for SAP solutionsSAP-certified Azure VMsAzure Monitor for SAP solutionsRISE with SAP on Azure
Google Cloud

Google Cloud options use certified memory-optimised machines in Mumbai with Delhi DR; the Agent for SAP is factored into the operations model.

SAP-certified Compute Engine M-series and X4Google Cloud's Agent for SAPBackup and DR ServiceRISE with SAP on Google Cloud

Strategic Choices With Clear Criteria

01

RISE with SAP or IaaS

RISE suits organisations that want one contract and SAP-managed technical operations, have limited Basis skills and accept subscription lock-in. IaaS suits those that value control of infrastructure, sizing, timing and partners, and have Basis capability in-house or through a partner. Compare on identical scope; RISE includes services that IaaS quotes often leave out.

02

Move ECC first or convert in one step

Move ECC to IaaS first when hardware fails before conversion can be planned, or when custom code exceeds what can be remediated before 2027. Convert in one step when the Readiness Check shows manageable simplification items and the business can absorb one major change. Two steps add one extra cutover but separate infrastructure risk from functional risk.

03

Timing against 2027

A brownfield S/4HANA conversion typically takes 9-18 months for mid-sized landscapes. Back-calculate from December 2027, avoid fiscal year-end in March, and leave a buffer. Extended maintenance to 2030 is available at a premium, which buys time but should be priced into the stay option, not treated as free.

04

Consolidation of group SAP instances

Consolidate when group companies share processes and chart of accounts, and integration costs between instances are high. Keep separate when entities have distinct regulators, listed-company reporting or divestment plans. Consolidation is easier during S/4HANA conversion than afterwards.

Six-Week SAP Strategy Assessment

01 · Weeks 1-2

Landscape and contract baseline

Systems, add-ons, contracts and support costs gathered.

02 · Weeks 1-3

SAP Readiness Check

Readiness Check run and simplification items reviewed with functional leads.

03 · Weeks 3-4

Option costing

Four options costed on like-for-like scope with quotes where available.

04 · Week 5

Risk, control and timing

Options scored and timed against 2027 and business calendar.

05 · Week 6

Board recommendation

Recommended path and business case presented to the CFO and board.

What you receive

SAP landscape and contract baseline
Readiness Check interpretation for conversion effort
Four-option five-year cost comparison
Risk, control and timing scorecard
Recommended path with decision gates

Decision Quality Indicators

KPI Typical target
Options compared on identical scope 4 of 4
Cost variance of chosen option at year one Within 15 percent
Decision made before procurement deadline Yes
Months of buffer before 2027 At least 6

Traps in SAP Cloud Decisions

Risk How NTSPL prevents it
Comparing a RISE subscription with hardware only Like-for-like scope including Basis, AMS, DR and upgrades in every option.
Underestimating custom code remediation Readiness Check results reviewed with functional leads, not just Basis.
Deadline pressure forces a poor contract Decision gates set early enough to negotiate with more than one provider.
Buyer comparison

RISE with SAP or S/4HANA on AWS, Azure or Google Cloud under our own licences?

Choose RISE with SAP when you want a single subscription covering software, infrastructure and SAP technical operations, have limited Basis skills and accept less flexibility in sizing, partners and exit. Choose S/4HANA on hyperscaler IaaS when you want control over infrastructure, timing, DR design and support partners, and have or can contract Basis capability. Cost comparisons must use identical scope: RISE quotes include technical managed services, upgrades and some tooling that IaaS quotes often omit, while IaaS lets you apply existing commitments and right-size more aggressively. For many Indian mid-sized SAP customers, the decision turns on skills and control rather than headline price.

Key facts: SAP Cloud Assessment

●SAP mainstream maintenance for SAP ERP 6.0 (EHP 6-8) ends on 31 December 2027, with optional extended maintenance to the end of 2030.
●RISE with SAP can be hosted on AWS, Microsoft Azure or Google Cloud.
●SAP Readiness Check analyses an ECC system for S/4HANA conversion, including simplification items, custom code and add-ons.

SAP Cloud Assessment: Frequently Asked Questions

How long does an SAP cloud assessment take?

About six weeks. The Readiness Check and contract gathering take the first two to three weeks; costing, scoring and the board recommendation take the rest. Multi-instance groups may need eight weeks. Running SAP Readiness Check needs a few days of Basis effort to apply notes and collect data.

What does an SAP strategy assessment cost?

Typically 20-30 consultant days, depending on the number of SAP instances and whether a RISE proposal needs detailed comparison. It is a fraction of the cost difference between options, which often runs into crores over five years. Normalising quotes from SAP and hyperscaler partners to the same scope is included in the fee.

What happens to ECC support after 2027?

SAP mainstream maintenance for ECC 6.0 enhancement packages 6-8 ends on 31 December 2027. Optional extended maintenance runs to the end of 2030 at an additional fee, after which customer-specific maintenance applies. Those fees belong in any stay option's five-year cost.

Can SAP data stay in India under each option?

Hyperscaler IaaS options can run entirely in Indian regions. For RISE, data location depends on the hosting region in the contract, so we check it alongside DPDP Act 2023 and any sector requirements before recommending. Contract terms on data location, exit and data return are reviewed with legal.

Is NTSPL independent of SAP and the hyperscalers?

We work with all three hyperscalers and the scoring is designed to be option-neutral. Every assumption is documented so your finance team can verify that the recommendation follows from the numbers. Any option-specific partner incentives are disclosed in the report.

What comes after the strategic decision?

A technical readiness assessment for the chosen option: SAPS and HANA memory sizing, OS and database versions, Unicode, interfaces and add-ons, leading to a migration plan. For RISE, SAP's own onboarding activities start at this point.