Payroll SaaS keeps month-end salary files on time through three platform incidents
Payroll and compliance software for 1,900 employer clients, about 6.5 lakh payslips a month · Azure Central India (Pune) with South India (Chennai) DR · 8 weeks including two month-end cycles
As-is situation
The platform ran payroll calculation on Azure App Service and Azure SQL Database, generating salary bank files that clients upload before bank cut-off times. Over 70% of runs happened between the 25th and the 1st. Any incident in that critical window was handled by whoever happened to be online, and support teams told clients different stories. Two earlier month-end slowdowns had pushed bank files past cut-off for 140 clients, which led to salary credit delays, penalty credits and three contract escalations.
- Month-end P1s had no fixed owner, so restoration averaged 2 hours 40 minutes
- Support gave 140 affected clients inconsistent updates in one incident
- A recurring SQL deadlock had caused three incidents without a problem record
Approach, tools and architecture
NTSPL defined month-end severity by the number of payroll runs blocked and the hours left before bank cut-off. During the last six days of each month, our incident commander is on dedicated standby with the client's lead engineer. Azure Resource Health and Service Health are checked in the first five minutes to separate platform faults from code faults. Azure Automation runbooks scale the SQL tier and move calculation jobs to a secondary queue. Support receives an approved update template every 30 minutes, and the deadlock was opened as a problem record and fixed through index changes.
Implementation approach
Measured results
Operational improvements
- Support quotes one approved status line to every client during an incident
- Month-end standby rota is published on the 20th of each month
Cost considerations
Dedicated month-end standby is priced as a six-day surge block on top of the monthly service. Scaling Azure SQL during incidents adds a few hours of higher vCore charges, far less than permanently sizing for the peak.
Return on investment
One cut-off miss had cost about ₹9 lakh in penalty credits and goodwill waivers. Avoiding any miss across three incidents, and retaining two at-risk enterprise renewals, paid for the service within the first quarter of operation.