Multi-state cooperative bank moves its AWS start date only once, with every gate dated
Multi-state cooperative bank, 118 branches, ₹9,000 crore deposits · Karnataka and Maharashtra · 4 weeks plus 30-day re-score
As-is situation
The bank's core banking ran with a CBS service provider, but loan origination, HRMS, treasury reporting, an email archive and 22 other systems sat in its own Belagavi server room on hardware out of warranty. IT had opened an AWS account on a corporate card a year earlier and built two test servers. The board had been told migration would start in April. There was no outsourcing policy covering cloud, no MFA on the root account and one engineer with an associate-level certification.
- 9 of 14 critical gates failed, including board approval and privileged MFA
- The shadow AWS account used a personal email for root and had no CloudTrail
- Only 1 of 14 IT staff held any cloud certification
Approach, tools and architecture
NTSPL scored all 42 gates with evidence and walked the regulatory gates through with the compliance head and company secretary. The outsourcing policy and provider risk assessment were drafted for the July board meeting. The shadow account was closed after its two servers were rebuilt in a new AWS Control Tower organisation in Mumbai with Hyderabad as the secondary region. Two engineers began certification, and a managed partner covered the first 90 days. The critical-path model showed August as the earliest honest wave-one date.
Implementation approach
Measured results
Operational improvements
- Cloud outsourcing added to the board's annual review calendar
- Break-glass access tested quarterly with a sealed-envelope procedure
Cost considerations
The assessment took 19 consultant days. The 90-day managed-partner cover cost about ₹7 lakh, far less than hiring two experienced cloud engineers in Belagavi at short notice.
Return on investment
The start date moved once, from April to August, rather than slipping quarter by quarter. Going live with board approval in place avoided a likely inspection observation and the remediation effort that would have followed.